The New Hall Build Project

Updates


The first site meeting between Iris Construction Projects Ltd, Chris Ham of Amber Projects and the representative trustees of Eastham Memorial Hall took place on 23rd July 2020 to discuss program of works, contract administration and site organisation.

The initial design meeting took place on 30th July 2020

The Start Date was 3rd August 2020 with a completion date of 14th December 2020. 

The working hours will be Monday- Friday 7.30am – 5pm Saturday 7.30am – 4pm.

Any large deliveries will be posted on Teme Eastham Facebook page and the website in advance wherever possible.


As we enter a new year the project end is in sight with a completion date now being the end of January for the main build itself. Once the main building is complete the ramp to the entrance door including resurfacing the car park can take place along with work on the new garden whicjh we have now raised over £6,000 towards.